It will be at least October before passengers are riding the Trillium Line, as OC Transpo and its partner continue to identify “some gaps and some issues” during testing on Ottawa’s new north-south light-rail transit line.
OC Transpo general manager Renee Amilcar says the transit service is not ready to say when the 21-day testing period will begin, or when the new line from Bayview Station to Riverside South will open to the public.
“We’ve reached several significant milestones and made substantial progress, but there is still critical work underway before we are confident the system is ready to proceed to trial running,” Amilcar told the light-rail transit subcommittee on Thursday, adding bugs are being identified and addressed during the daily testing.
The new line between Bayview Station and Limebank Station, with a spur to the Ottawa International Airport, was originally scheduled to open in August 2022, but construction delays have pushed back the opening date. Staff say once trial running begins, it will be at least four to six weeks before the Trillium Line will open to the public.
“A lot of work has been completed and we are much closer to the start of trial running; however, we still need to finish the pre-trial running prerequisites and grow the system reliability. These two work activities are occurring in parallel,” Richard Holder, acting director of the rail construction program, told councillors.
“We can see the steady improvement of system performance but more work is required. Once trial running is underway, we expect a minimum of four to six weeks to get to substantial competition and to obtain the needed regulatory approvals.”
The new Trillium Line station at Carleton University. (OC Transpo presentation)
OC Transpo and its partner, TransitNEXT, have a list of nine prerequisites before launching the trial running, including testing the integrated System Infrastructure, fully testing the complete fleet, signalling and train control system testing, there are no outstanding defects affecting rail systems — track, signals and communications — and there are no major defects, safety defects, or incomplete vehicle modifications programs.
“We are doing the final tidy up,” Holder said about work to complete the prerequisites.
All 13 stations have obtained occupancy permits, and elevator inspections have been completed and final certificates issued.
OC Transpo and TransitNEXT are required to do a 21-day testing period before the system is cleared for launch. The testing period includes a 14-day service reliability test with the Trillium Line running a full regular service schedule to simulate passenger service and a seven-day “failure scenario management period.”
Staff have said councillors will receive a memo confirming when the 21-day testing period will begin, and daily updates outlining the scoring and any deficiencies.
“We are seeing good vehicle reliability,” Holder said. “The more that we do exercise trains on the line, we do see issues but they get resolved. A key message here is that we are not seeing a systematic problem across the two fleets that we do have, but we have bugs that need to be fixed.”
The Dow’s Lake station along the Trillium Line. (OC Transpo presentation)
A presentation for the LRT subcommittee said for three weeks following trial running, OC Transpo and TransitNEXT maintenance personnel will continue “final preparations and readiness activities for the launch of the system.”
The activities during the three week period will include “exercising all aspects of daily service including launch and reduction of trains, maintenance of vehicles and related infrastructure,” conducting drills and reviewing standard operating procedures.
The 16-kilometre Trillium Line will run between Bayview Station and Limebank Station, with a 4-km link from South Keys Station to the Ottawa International Airport.
On July 18, staff said OC Transpo and TransitNEXT were in week two of the eight to 10 week testing and trial running period ahead of the launch of the Trillium Line, which suggested an opening date in mid-September. The four to six week timeline once testing begins puts an opening date in early to mid-October.